CDM dutyholder checker
Five questions and you get a map of who holds which duty on your project, including where the roles have landed by default if nobody was appointed.
This tool gives general guidance from the answers you type. It is not legal advice about your project, and it cannot see your drawings or your site. Where a project is unusual the answer is a conversation rather than a checker. How we write this.
The five dutyholders
CDM 2015 works by giving named duties to five kinds of party. Every project has all of them in some form, even a small one, and the roles do not disappear when nobody is appointed. They move.
Where the defaults come from
| If nobody is appointed | Domestic client | Everyone else |
|---|---|---|
| Principal designer | Regulation 7(2): the designer in control of the pre-construction phase | Regulation 5(3): the client carries the duties |
| Principal contractor | Regulation 7(2): the contractor in control of the construction phase | Regulation 5(4): the client carries the duties |
| Client duties | Regulation 7(1): the principal contractor, or the principal designer by written agreement | Stay with the client. Not transferable |
Sources
- CDM 2015, regulation 5 legislation.gov.uk
- CDM 2015, regulation 7 legislation.gov.uk
- CDM 2015, regulation 9 legislation.gov.uk
- CDM 2015, regulation 12 legislation.gov.uk
- CDM 2015, regulation 15 legislation.gov.uk