What are the principal contractor's duties under CDM 2015?

Short answer

The principal contractor must plan, manage and monitor the construction phase and coordinate health and safety through it, under regulation 13. They must draw up the construction phase plan and keep it current under regulation 12, provide site inductions, keep unauthorised people out, make sure the Schedule 2 welfare facilities are provided, and consult and engage with workers under regulation 14. On a domestic project they also pick up the client's duties under regulation 7(1).

The duties

  1. Plan, manage and monitor the construction phase

    Regulation 13(1), coordinating health and safety through it so the work is carried out without risks so far as is reasonably practicable.

  2. Draw up the construction phase plan

    Regulation 12(1), before setting up the site, and keep it reviewed, updated and revised under regulation 12(4).

  3. Organise cooperation between contractors

    And coordinate their work, so that one trade's activity does not create a risk for another's.

  4. Site induction, and keeping people out

    Regulation 13: inductions for everyone working on site, and reasonable steps to prevent unauthorised access.

  5. Welfare

    The Schedule 2 facilities: sanitary conveniences, washing facilities, drinking water, changing rooms and lockers where needed, and rest facilities.

  6. Consult and engage with workers

    Regulation 14. Arrangements for workers to cooperate in developing, promoting and checking the effectiveness of health and safety measures, and consulting them on matters affecting their safety.

  7. Feed the health and safety file

    Regulation 12(7): give the principal designer any information relevant to the file. If the principal designer leaves first, regulation 12(8) hands the file over to the principal contractor to finish.

The extra layer on domestic projects

Regulation 7(1) moves the domestic client's duties in regulations 4(1) to (7) and 6 onto the principal contractor, unless there is a written agreement for the principal designer to take them. So on a domestic project the principal contractor is carrying two sets of duties: their own, and the homeowner's.

And under regulation 7(2), if the homeowner appointed nobody, the contractor in control of the construction phase is the principal contractor by default, whether or not they know it.

What is not the principal contractor's job

Written by James Nicholson, BSc (Hons) Architectural TechnologyLast reviewed 28 August 2026How we write this

Sources

  1. CDM 2015, regulation 12: construction phase plan and health and safety file legislation.gov.uk
  2. CDM 2015, regulation 13: duties of a principal contractor legislation.gov.uk
  3. CDM 2015, regulation 7: application to domestic clients legislation.gov.uk
  4. HSE: principal contractors, roles and responsibilities hse.gov.uk
  5. Managing health and safety in construction, L153 HSE guidance on the Regulations