What is a health and safety file?

Short answer

A health and safety file is a file appropriate to the characteristics of the project, containing the information about it likely to be needed to keep people safe during any later work on the building. The principal designer prepares it under regulation 12(5), and it is required only on projects involving more than one contractor. At the end of the project it goes to the client, who keeps it and passes it on if they sell.

What goes in

HSE guidance lists what should be considered for inclusion:

What to keep out

Guidance is specific: the file should not include things that will be of no help when planning future construction work, such as the pre-construction information, the construction phase plan, contractual documents or safety method statements. The information must be in a convenient form, clear, concise and easily understandable.

Why that discipline matters. The file is read by somebody in a hurry, years later, deciding whether it is safe to open a wall. Everything that is not about that decision makes the decision harder.

Who keeps it and for how long

The client, for as long as it is relevant, which HSE guidance describes as normally the lifetime of the building. It can be paper, electronic or any other durable form. If the client disposes of their interest in the building they must give the file to whoever takes on the client duties and make sure they know what it is for. If they sell part of a building, the relevant information is passed or copied to the new owner.

On the next project it becomes something else

The loop worth understanding: on the next project on that building, the health and safety file is pre-construction information. Regulation 4 makes the client provide relevant information they hold, and HSE guidance names an existing health and safety file as one of the first things to look for. A file written carelessly is a problem for a project that has not started yet.

principal designer helpsthe client put it togetherPre-constructioninformationdrawn up by the principalcontractor before work startsConstructionphase planhanded to the clientat the endHealth andsafety filereg 12(3)and becomes pre-construction information for the next project on the building
The information chain CDM 2015 sets up. Pre-construction information is what the principal contractor builds the construction phase plan on, which is why regulation 12(3) makes the principal designer hand it over. The health and safety file closes the loop: it is written for whoever works on the building next, and on their project it becomes pre-construction information.

Written by James Nicholson, BSc (Hons) Architectural TechnologyLast reviewed 28 August 2026How we write this

Sources

  1. CDM 2015, regulation 12: construction phase plan and health and safety file legislation.gov.uk
  2. CDM 2015, regulation 4: client duties in relation to managing projects legislation.gov.uk
  3. Managing health and safety in construction, L153 HSE guidance on the Regulations

Find out where your project stands

The free checker asks six questions and tells you whether the appointment is required, and why.

Open the checker →

Not sure yet? go straight to a fixed fee.