What happened to the CDM coordinator role?
Short answer
The CDM coordinator was created by CDM 2007 and removed when CDM 2015 came into force on 6 April 2015. Its replacement is the principal designer, which is a materially different role: the coordinator advised the client from alongside the project, while the principal designer must be a designer with control over the pre-construction phase, sitting inside the design process rather than beside it. The title still appears on websites and in old documents, but the appointment no longer exists.
What changed, and why it matters
| CDM coordinator, CDM 2007 | Principal designer, CDM 2015 | |
|---|---|---|
| Who could hold it | Anyone competent, commonly a standalone consultant | A designer with control over the pre-construction phase |
| Position on the project | Advising the client, alongside the design team | Inside the design process, coordinating it |
| Domestic projects | Largely outside the regime | Inside it, with regulation 7 reallocating client duties |
| Notification threshold | Different, and a common trigger | Regulation 6, and uncoupled from the appointment question |
The most consequential change for small projects was not the title. It was that CDM 2015 brought domestic work properly into scope.
Why you still see the old title
Three reasons. Consultancy pages written before 2015 and never updated. Firms who keep the phrase because clients still search for it. And documents on older buildings, where a health and safety file may genuinely have been prepared by a CDM coordinator under the earlier regulations.
An existing health and safety file from a CDM 2007 project is still useful information, and under regulation 4 it is exactly the sort of thing a client should be handing over as pre-construction information at the start of the next project.
Sources
- The Construction (Design and Management) Regulations 2015 legislation.gov.uk
- CDM 2015, regulation 4: client duties in relation to managing projects legislation.gov.uk
- CDM 2015, regulation 5: appointment of the principal designer and the principal contractor legislation.gov.uk
- Managing health and safety in construction, L153 HSE guidance on the Regulations
Find out where your project stands
The free checker asks six questions and tells you whether the appointment is required, and why.
Open the checker →Not sure yet? go straight to a fixed fee.